At Point dd, Clause 2, Article 89 of the Law on Construction 2014 stipulates, “Construction works in projects of industrial parks, export processing zones, high-tech zones with detailed planning 1/500 have been approved by State agencies. competent to approve and appraise construction designs according to the provisions of this Law” are exempt from construction permits.
Therefore, the construction of works in industrial clusters is not exempt from construction permits as prescribed in Point dd, Clause 2, Article 89 of the Law on Construction.

Works exempt from construction permits include:
State secret works, works built under urgent orders and works located in the area of two or more provincial-level administrative units;
Works under construction investment projects approved by the Prime Minister, Ministers, Heads of ministerial-level agencies, Presidents of People's Committees at all levels;
Temporary construction works to serve the construction of main works
Works built along lines outside urban areas but in accordance with construction plannings already approved by competent state agencies or approved by competent state agencies in terms of work alignments;
Construction works under projects of industrial parks, export processing zones and high-tech zones with detailed planning 1/500 approved by competent state agencies and appraised for construction designs according to regulations of law. This Law;
Houses under urban development projects, housing development projects with a scale of less than 7 floors and a total floor area of less than 500 m2 with a detailed 1/500 plan approved by a competent state agency

The work of repairing, renovating and installing equipment inside the work does not change the load-bearing structure, does not change the use function, does not affect the environment and safety of the work;
Repair and renovation works that change the exterior architecture not adjacent to roads in urban areas with requirements on architectural management;
Technical infrastructure works in rural areas only require the preparation of economic - technical reports on construction investment and in areas where there is no approved detailed construction planning for rural residential quarters;
Construction works in rural areas in areas where there is no approved urban development planning and detailed construction planning; separate houses in the countryside, except for separate houses built in conservation zones, historical-cultural relics.
Process of applying for a factory building permit:
1. Order of execution:
– Step 1: Prepare the required documents.
– Step 2: Submit the application at the receiving and returning results section of the People's Committee of the commune or ward.
– Step 3: The City Urban Management Department receives the dossier and conducts verification and submits it to the City People's Committee for licensing.
– Step 4: Organizations and individuals receive permits at the Department of receiving and returning results of the City People's Committee.
2. Method of implementation: Directly at the administrative office.
3. Profile composition:
- An application for a construction permit;
- A copy of one of the papers proving the land use right as prescribed by the law on land;
- A copy of the project approval decision or investment decision;
- Construction design drawings;
- A declaration of capacity and experience of the design organization or individual who is in charge or in charge of construction design, enclosed with a copy of the practice certificate of the design manager or chairperson;
4. Number of dossiers: 01 set.
5. Processing time: 15 working days from the date of receipt of complete and valid dossiers, excluding holidays and weekends.
6. Subjects performing administrative procedures: individuals, organizations.
7. Agency implementing administrative procedures: Urban Management Division.
8. Results of administrative procedures: License.
If there are any related questions that need to be answered, please contact us to be answered in the most specific way.
BIC is committed to providing customers with the best building service, office building, high-rise apartment building. By the enthusiasm and unrelenting efforts of all officials and employees. Especially, we have conquered many big projects and gained the confidence and satisfaction of the "Big Men" in the world who came to Vietnam to invest in the construction.
BIC is very pleased to serve you with the spirit: "COOPERATE TO DEVELOP TOGETHER"
BIC CONSTRUCTION ARCHITECTURAL JOINT STOCK COMPANY
Ho Chi Minh Branch: 7th Floor, Gia Dinh group, 566 National Highway 13, P.Hiep Binh Phuoc, Thu Duc District, Ho Chi Minh City
☎️ Hotline: 0901.815.069
Mail marketing: marketing@bicons.vn
Hanoi Branch: 4th Floor, HUD3 Tower, No. 121-123 Pho To Hieu, Ha Dong District - Hanoi.
☎️ Hotline: 0243.91.92.789
Mail: bic@bicons.vn - Fax: (028) 38 800 892
Mail marketing: marketing@bicons.vn
Website: bicons.vn - bicjsc.com