The factory building process is formed through practical experience in building factories at the request of investors in different industries. But basically in the basic factory construction process, it is analyzed in detail to easily manage and monitor the construction process closely to ensure the quality of finishing the work.
To make it easier for everyone to understand, the factory construction process is done, let's learn the following information:
- Surveying the location and construction site of the factory and giving the appropriate design plan.
- Propose a plan on technology and technical infrastructure to have a specific authentic construction plan
- For factories requiring architectural design structures such as offices and auxiliary items, etc., there will be a logical layout plan.

- Optimizing the options of regulations on environment, fire prevention according to the regulations of the industrial park or industrial zone cluster.
- Choose the foundation structure plan suitable for the geology at the place of construction of the factory
- Applying standard standards in accordance with the law to ease the completion procedures.
Design construction technical documents
- Construction technical dossiers need to have drawings describing the total ground or drawing of the project route plan to be built in each phase.
- Workshops with technology requirements need to update production line diagrams or drawings
- Workshops with architectural requirements need to draw architectural plans
- Prepare drawings with structural plans.
Construction drawing design content includes design explanation, design drawing or construction survey documents related to the work estimate.
Contents of construction drawing design must be full of technical information, materials used and structural details in accordance with application standards. Design drawings must meet all conditions for construction.
The process of building and installing a basic factory is common in sequence
+ Construction of the foundation
+ Construction of factory infrastructure
+ Erection of steel frame and workshop accessories
+ Construction of factory cover
+ Construction of technical systems
+ Finishing
+ Sanitize and put into production operation
In order for the desired industrial factory construction process to be highly effective in terms of cost and function, it is necessary to carefully calculate the construction schedule according to each stage according to the design. It is important to complete the project according to the commitment to meet the investor's mind.
Installing foundation bolts is the first and fundamental step in the process. This work requirement is that the bolts are installed correctly. If there is a deviation in this work, it will affect the erection of steel structure beams and columns.

Foundation bolts need to be rigidly connected by loading into the foundation reinforcement system
The installation of foundation bolts needs to be carried out after the erection of reinforcement and foundation reinforcement is completed, which will ensure the stability of the constructed reinforced reinforcement system. The foundation bolt system is bolted, accurately positioned thanks to the experience of the operator with the support of tools such as surveying machine, leveling machine and fixed welding to the foundation steel system.
Finishing the installation in preparation for pouring concrete, bolts are carefully sealed so that the thread ends are not dirty to reduce the impact of the environment.
Before erecting the steel structure of the industrial factory, the survey of the current site, service roads, crane operation area, material gathering location.... Making construction drawings and safety measures for the erection of industrial factories
Design components are fully assembled by the transport workshop at the construction site. The technical team will carry out the erection and connection of the components together. With the support of the chain hoist, lift the steel structures to the right position to be assembled.

+ Installing hard lock space
+ Set up the first truss
+ Installing the second rafter beam
+ Complete the lock
+ Installation of all truss frames and purlins
+ Install gable rafter
+ 100% complete installation and anti-purlin
For factories with corrugated iron roofs
+ Drag the roof to the roof
+ Place each roofing sheet on the slide, between thanks to the 6mm iron hooks that slide on the cable
+ The worker pulls him and runs to the roof carrying the roofing sheet to the location where it needs to be roofed.
+ After the corrugated iron is up to the rafter, manually transfer it to the gutter with even edges.

Installation of all corrugated iron for the roof
Check to see if the corrugated board is in the correct position
If the gap from the last corrugated sheet to the gable wall or the side facade is less than 0.5 sheet width, it can be covered with flashing or capping. All birch must be covered and fastened
In case of installing corrugated iron wall
When installing corrugated iron walls, construction will build walls from 1m2 to 1m4 high, then proceed to install corrugated iron walls.
Pulling corrugated iron by rope tied to corrugated iron
The ELBC shock-proof circuit breaker is located near the ground.
The standard factory erection process is still important in the steel frame erection stage. Thanks to the steel frame processing carried out in parallel with the construction according to the design drawings, the construction time is faster. The quality of the works is guaranteed to increase the service life when the factory is put into production.