During the construction of the factory, both the investor and the construction contractor are interested in building permits in the industrial cluster. Factories built in industrial zones often have to comply with regulations and paperwork according to the industrial park management board.
In a specific case, the investor is leased 2 hectares of land by the State in an industrial park cluster, already has an investment project and the total area is approved at the rate of 1/500. So how can businesses get a construction permit in an industrial cluster?

With 10 years of experience in the field of factory construction, we can provide information about
Pursuant to Articles D, Clause 2, Article 89 of the Law on Construction, for "Construction works belonging to projects of industrial parks and high-tech export processing zones with detailed planning 1/500 already approved by state agencies." competent to approve and appraise construction designs according to the provisions of the Construction Law shall be exempted from construction permits.
The construction of works in industrial clusters is not exempt from construction permits as prescribed in Clause 2, Article 89 of the Law on Construction.
- Works that are state secret, works built under urgent orders and works located in the area of two or more provincial-level administrative units.
- Temporary construction works in service of construction shall be decided on investment by the Prime Minister, Ministers, Heads of ministerial-level agencies, chairpersons of People's Committees at all levels.
- Temporary construction works to serve the construction of main works
- Works built along lines outside urban areas but in accordance with construction plannings already approved by competent state agencies or approved by competent state agencies in terms of work alignments.
- Construction works for projects of industrial parks and export processing zones of high-tech zones with detailed planning 1/500 approved by competent state agencies and appraised for construction designs in accordance with the Law on Construction. this
Housing under urban development projects, housing development projects with a scale of less than 7 floors and a total floor area of less than 500m2 with a detailed 1/500 plan approved by a competent state agency
- Works to repair, renovate and install equipment inside the works without changing the load-bearing structure, without changing the use functions, without affecting the environment and safety of the works;
- Repairing and renovating works that change the exterior architecture not adjacent to roads in urban areas with requirements on architectural management;
- Technical infrastructure works in rural areas only require the preparation of economic - technical reports on construction investment and in areas where there is no approved detailed construction planning for rural residential quarters;
- Construction works in rural areas in areas where there is no approved urban development planning and detailed construction planning; separate houses in the countryside, except for separate houses built in conservation zones, historical-cultural relics.