Applying for a CONSTRUCTION PERMIT IN LONG AN PROVINCE Industrial Park

When constructing any works in the industrial zone, a construction permit is required before the new works can be constructed. The application for a construction permit is a mandatory legal procedure for the work to be built, helping to legalize the completion of the project.

When constructing any works in the industrial zone, a construction permit is required before the new works can be constructed. The application for a construction permit is a mandatory legal procedure for the work to be built, helping to legalize the completion of the project.

This proves that the owner's ownership of the factory is an immediate property on the land in that industrial park. Carrying out the procedures for applying for a factory building permit, the investor needs to obtain a permit for approval of the investment location first.

Then proceed to make environmental permits, including the project of environmental impact assessment report or environmental protection plan, fire prevention and fighting license.

Applying for a CONSTRUCTION PERMIT IN LONG AN PROVINCE Industrial Park

Once the above documents have been prepared, the next step is to proceed with the procedure for applying for a factory building permit. In this article, BIC guides the specific steps of procedures for building construction permits in Long An according to the order BIC has done for factory investors in Long Hau Industrial Park, Hoa Binh Long An.

Process of preparing documents

Prepare documents to apply for construction permits according to state regulations

Submit the application at one door of the reception and return department of the People's Committee of District, Huyen (if applying for a construction permit as an individual).

File the application at the People's Committee of the province or city if it is an enterprise or company organization.

The Urban Management Department, the Department of Construction conducts verification of documents and issues permits to build factories for Individuals, Organizations, Enterprises...

Enterprises, organizations and individuals receive results at the Department of receiving and returning results where they have submitted documents.

The process of applying for a construction permit in Long Industrial Park is carried out in such a sequence that if there are any shortcomings, the receiving place will indicate that it is necessary to supplement the necessary documents that can be approved and approved until the date of issuance of the certificate. specific factory building permits.

Dossier to apply for a factory building permit includes:

- An application for a construction permit made according to the form

- Certificates of land use rights

- Factory construction design drawings

- Certificate of design approval for fire prevention and fighting

- Environmental license

- Investment policy (if the land is outside the industrial park)

- Business license of the design company

- Experience drawing of the design organization. The practicing certificates of architects, engineers, electricity and water of the design leader

In the process of preparing and filing the application for a construction permit, there will be other cases that arise.

A construction permit is a type of completely new construction procedure or a construction permit on top of an existing construction permit and an application for additional construction.

Besides, if the construction period has been granted but the factory has not been completed, additional procedures for extending the construction permit will be carried out.

Specifically, before the construction permit expires, if the work has not been started, the investor must request the extension of the construction permit. Each construction permit can only be renewed up to 2 times. Each renewal period is 12 months. When the construction permit extension period expires but construction has not yet commenced, the investor must submit a dossier of application for a new construction permit.

Dossier for building permit extension

- Application for extension of construction permit

- The original of the issued construction permit

In case the construction permit is granted for a separate house with an expired period of time when it is stated in the permit, but the planning has not yet been implemented, the owner of the work or the person assigned to use the work shall request to: The construction permit-issuing agency considers extending the existence time until the planning is implemented. The duration of the work's existence is immediately recorded in the issued construction permit with a definite term.

 