Contents of a contract template in which the parties agree on terms to ensure the interests of the parties. The latest updated factory contract template has been revised according to separate agreement requirements, if any.

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
……,day month Year…….
CONTRACT FOR BUILDING PRECAUTION FACTORY
Number: ……./HĐTCNTTC
- Pursuant to the Commercial Law of the Socialist Republic of Vietnam in 2005;
- Pursuant to the Civil Law of the Socialist Republic of Vietnam signed on January 24, 2015;
-Based on the Construction Law of the Socialist Republic of Vietnam in 2014
-Based on the functions, duties as well as capabilities of the two parties
Today on …..month…..….., at address…………., we include:
Party A: Company .....
Address:
Phone: ……………………………. Fax…………………………….
Tax code: ………………………………………………………………..
Legal representative : ……
Position: Director
Account number:………………………………………………………………………………..
Bank:………………………………………………………………………………….
prefabricated factory construction contract
Party B: Nguyen Thi B
CNIC:
Address:
Phone: ……………………………. Fax…………………………….
Account number:………………………………………………………………………………..
Bank:………………………………………………………………………………….
Together they discussed and reached the following agreements:
Article 1: Content of the agreement
Party A and Party B agree on the fact that Party B undertakes the construction of pre-engineered steel buildings for Party A and Party A is responsible for accepting payment for Party B.
Article 2. Subjects of the Contract
The subject of the contract is a pre-engineered steel building with the following construction process defined.
Article 3. Quality of raw materials
Ensuring the quality of raw materials according to the agreement of the two parties specified in Appendix 1.
Article 4. Construction process
Phase 01: Design of pre-engineered steel buildings
-Designing architectural drawings
- Deploy machining drawings
Stage 02: Processing steel structures
From the steel plates, proceed to cut according to the drawing table into loose billets, bring the chamfer, then switch to the welding job of two billets together. The machined plate will be punched with connection holes for bolting, in order to connect the steel structures together.
Assembly stage:
In order to insert the member into the mold, the members will be straightened, then assembled into a complete member by temporary welds.
Link welding: download factory construction contract template
Temporary welded members will be uniformly welded by different methods.
Editing :
Welding will not avoid the case of structural distortion. To overcome this situation, it is common to use hydraulic motors to complete the technical requirements.
Phase 03: Installation at the site
Before installing the cipher plate to the rafter body, the two ends of the member must be sawed.
Surface cleaning:
The surface of the components must be cleaned by a blasting system, just to create a roughness so that the surface has a certain grip for the painting process.
Finishing paint:
This is the final stage of the machining process. Paint quality and structural aesthetics depend a lot on this stage.
Transportation and erection at the site:
Factory finished components will be carefully packed; to limit scratches; collision during transportation. Components assembled at the construction site will be carefully preserved. The most important thing in the process of erection at the site; That is, the engineers understand the detailed layout of each component. Above all, comply with the installation requirements; to ensure the quality and safety of the works; and construction workers.
Article 5. Construction duration
-Construction within ……, from date…month….year…. to ……month…. five…..
-Ensure construction progress: Party B must usually notify Party A by email about the construction progress, every month .....times. Or Party A can directly supervise the construction.
-After the construction deadline, but Party B still has not completed the work, it can be negotiated with Party A to extend the time in ....days to ensure the quality of construction. If after the extension period, Party B still has not completed the work, Party B will be fined an amount equal to ... % of the contract value and Party A will unilaterally terminate the Contract with Party B without paying compensation. usually.download factory construction contract template
Article 6. Construction safety
-Party B must ensure safety in construction in accordance with the law to avoid accidents or incidents
-If there is an accident or incident during the construction process and Party B is the one who causes the fault, then Party B must be fully responsible before the law and compensate for the damage to Party A (if any).
Article 7. Construction acceptance
-Based on National Standard TCVN 10307:2014 on Steel Bridge Structures – General technical requirements for fabrication, assembly and acceptance and agreement of the parties
– Party B must ensure the standards agreed by the two parties. If Party B complies with the standards, does not guarantee the construction quality and causes damage to Party A, then Party B must compensate Party A based on the extent of the incident.
Article 8. Contract value
Total cost:…..Including:
-Design drawings
-Material processing
-Assembly at the site
Article 9. Deposit
-Party A will make a deposit to Party B: …..% of the order value equivalent to ……VND when signing this contract to ensure the performance of Party B's obligations. Download the factory construction contract template
–The amount will be refunded or deducted to fulfill the payment obligation of Party A.
-If Party A refuses the delivery
Article 11. Responsibilities of the Parties
1. Responsibility of Party A
- Handover the construction site to Party B for construction as required.
– Pay each time to Party B according to the progress and completed work volume specified in this Contract
-Create favorable conditions for Party B to construct
2. Responsibilities of the OVERVIEW
-Provide party A with a construction cost estimate. The estimate sheet is an integral part of the Contract.
– Appoint qualified and responsible people to supervise the construction and storage of materials at the construction site, in order to ensure that the volume and quality of the work are ensured to the required standards. Download factory construction contract template
-Notify in writing to Party A the name of the Construction Manager who is most responsible for engineering at the construction site so that Party A can discuss together during the construction process, answer questions and meet construction requirements. construction of Party A quickly, accurately and timely.
– Ensure that the means of communication such as phone and fax of Party B are always available and transparent to ensure that Party A's information reaches Party B quickly and accurately to achieve the highest quality results. quantity and time for the project.
- Provide adequate materials and labor to ensure construction progress.
– Complete and hand over the construction items within the time limit specified in this Contract.
– Be obligated to pay the fine for late completion of the work as prescribed in this Contract.
-Equipping power supply to ensure the construction process.
– Proceed to apply for procedures for the construction department of Party B to temporarily reside in the locality during the construction period.
- Ensure public order and security, protect construction materials and means.
– Ensure and take responsibility for the safety of workers. Self-managing the construction workforce of Party B, not allowing any disputes between Party B's employees and other third parties or between Party B's internal parties.
- Comply with the relevant requirements of Party B on the necessary details so as not to affect the quality and progress of the work.
Article 12. Termination of contract
-When the two parties have completed the obligations in the contract and made a record of contract liquidation
-When the performance of the contract does not bring benefits to the parties
-When Party A terminates the contract, it must pay wages corresponding to the work performed.
-When Party B terminates the contract, he will not receive remuneration corresponding to the work he has done
When either party terminates the contract and causes damage to the other party, it must compensate both parties for damage.
Article 13. Force majeure
-In the event of force majeure as prescribed in civil law (earthquake, storm, flood, fire, war, government actions, etc., which cannot be prevented or controlled), the obstructed party can the right to suspend the performance of its obligations for a period of ....months without being responsible for any consequences caused by delay, damage or related loss, and must notify by mail immediately notify the other party of such force majeure. The two sides will work together to resolve the consequences in the most reasonable way.
- In case the two parties cannot agree, the contract will be terminated.
Article 14. Dispute settlement
In the event of a dispute arising, the parties agree to prioritize settlement through exchange and negotiation. This exchange and negotiation is done ….times and must be made in writing. If after… the last time the exchange or negotiation is held, the two parties cannot agree to settle the dispute, one or both parties have the right to bring the dispute to a competent Court for settlement in accordance with current law. onion.
Article 15. Contract validity
The contract takes effect from the date of…month….year, made into …. copies have the same legal validity, Party A keeps … copies, Party B keeps … copies.
Party A's signature Party B's signature