The procedure for building a factory in an industrial park is quite important to know when investing or building a factory in an industrial park. Through the article, we will grasp the steps to implement the cabinet to help you be more active in the process of self-administering administrative procedures and prepare the necessary documents to apply for a permit to build a factory or warehouse in Vietnam. industrial parks according to the provisions of the Law on Construction 2014 on the issuance of construction permits.
For construction works that are not included in the exemption of construction permits, the procedures and steps for implementation
Step 1: Prepare the required documents
In which, the application for a permit to build a factory in an industrial park will have all kinds of papers
+ An application form for a construction permit
+ Certificate of investment or notice of investment acceptance of the management board of the industrial park, a photocopy
+ Commitment to environmental protection (certified copy). Certificate of appraisal and approval of fire prevention and fighting (certified copy) with 01 set of drawing documents stamped with fire protection approval stamp (photocopy)
+ The original of the work construction investment project
Project explanation
Technical or construction design drawings with verification stamp of a functional consulting unit
+ Business registration certificate of the design consultancy unit and practice certificate of the chair of design subjects (certified copy)
+ The original report on verification results of technical design or construction drawings, enclosed with the business registration certificate of the verification consulting unit (certified copy)
+ The original of the geotechnical survey report enclosed with the business registration certificate of the surveying unit and the practicing certificate of the head of the geological survey of the works (certified copy)
Step 2: Submit the application file at the receiving and returning results section of the People's Committee of the commune or ward
Step 3: The city's urban management office receives the dossier and conducts verification and submits it to the city's People's Committee for licensing.
Step 4: Organize individuals to receive permits at the receiving and returning results section of the City People's Committee
Directly at the administrative office
Processing time is 15 working days from the date of receiving complete and valid dossiers, excluding holidays and weekends
Individuals or organizations carrying out administrative procedures
The Urban Management Department carries out administrative procedures
Results of administrative procedures for granting construction permits