(Construction) - The Ministry of Construction received a document from the Transaction Office I of the Vietnam Development Bank guiding the adjustment of the work construction permit.

Vietnam Development Bank (photo: Internet).
After considering, the Ministry of Construction has the following comments:
Accordingly, the office building of Transaction Office I of Vietnam Development Bank at 185A, Giang Vo Street, Dong Da District, Hanoi City has been notified by the Hanoi Department of Construction of the design appraisal results. establishment No. 292/SXD-TD dated 07/02/2007, granted construction permit No. 07 GP/SXD on January 22, 2009 and extended the construction permit in Document No. 05 CV/QLCP-SXD dated 01 02/2010.
During the construction process, the investor has adjusted some contents compared to the construction permit. At Notice No. 25/TB-TTr(D1) dated June 11, 2013 on the results of construction inspection, the Inspector of Hanoi Department of Construction asked the investor to contact the Hanoi Department of Construction to adjust the content of the issued construction permit in accordance with current regulations before continuing with the construction of the next items.
According to the content of Document No. 420/NHPT.SGDI-XDCB above, Notice No. 1148/GD-GD3 dated October 4, 2018 of the State Assessment Department on construction quality - Ministry of Construction on the results inspecting the acceptance of completed works, at the time of inspection, the works under the project have been completed and the investor has put the works into operation and use since 2015 without being approved by the competent authority. construction specialists appraise and approve the adjusted design, have not yet adjusted the construction permit, and organize the inspection and acceptance work.
However, because the work has been put into operation and the law on construction, there is no provision for appraisal at a specialized construction agency or adjustment of the construction permit in this case. Therefore, it is recommended that the investor contact the local construction order management agency for guidance on not fulfilling the requirements of the Inspector of the Hanoi Department of Construction at the notice of construction inspection. construction mentioned above.